ADVANTAGES
 | Contractor adds lower than normal
percentage of all costs for his over head and profit. |
 | Fixed or decreasing fee basis removes
contractors incentive to increase costs or cut quality. |
 | Owner profits from cost reductions. |
 | Construction time is reduced by concurrent
engineering completion. Low engineering costs due to short term engineering effort limited
to project needs only. |
 | Owner retains control of cost and schedule. |
 | Scope changes are handled expeditiously. |
 | Owner caused schedule interruptions generally
result in crew reductions or reassignment with minimum cost impact. |
LUMP SUM
ADVANTAGES
 | Competitive biding assures low cost option and
advance knowledge of costs. |
 | Contractor assumes cost overrun risk. |
 | Use of reliable contractor results in minimal
owner supervision. |
|
|
DISADVANTAGES
 | Cost cannot be entirely
predetermined. This may be minimized by competitive bidding of subcontractors and material
suppliers. |
 | Owner assumes cost and schedule risks. |
 | Keeping costs low is dependent on integrity of
contractor. |
 | Accounting of time sheets and material used is
required. |
LUMP SUM
DISADVANTAGES
 | Engineering must be 100% complete for effective
bidding. |
 | Contractors risk protection allowance adds
20-30% to estimated cost. |
 | Contractor may attempt to cut quality to maximize
profits. |
 | Cost reductions are not returned to owner. |
 | Owner changes to scope may be overpriced. |
 | Owner schedule interruptions may result in cost
escalation. |
|